RW was asked to complete a survey of the North half of the Wastewater Treatment Plant for some upcoming site improvements. Due to the nature of the site and the number of tight spaces to be surveyed, we made the determination that utilizing scanning in conjunction with our traditional survey tools would allow us to complete the job for a lower overall cost without slowing down the timeline for completion. Our Survey team collected data on the wide-open areas and ran control throughout the site to lock down the scan data. Our Scanning team collected data on the denser areas. In all, scanning for 5 days was able to offset a projected 4 weeks of traditional surveying.